Maintenance for reconditioning or change of Trims

  • 1. On-site lifting of valves that require reconditioning maintenance of internal parts including seal areas.
  • 2. The maintenance service will be quoted based on the opinion of the enhanced visit and on the client's requirements for approval.
  • 3. Since this maintenance must be performed at the plant, the collection of the valve on site will be coordinated with the client once the OC has been placed.
  • 4. This maintenance does not include evaluation of the valve pressure vessel such as body, bonnets, yokes, ends, internal castings etc.
  • 5. The plant will manufacture the required parts and will proceed to prepare the bodies, end bonnets and, if necessary, machine the required parts, clean them using scale removers.
  • 6. Once the work is finished, an operation test and hydrostatic tests will have to be carried out.
  • 7. Sand blast and paint with the standard paint applied at Walworth for shipment.
  • 8. A maintenance certificate is issued with the scope carried out so that from this date the warranty period is considered, which will be 1 year in the parts that were replaced.